Flat-for-Land Construction Contracts in Urban Transformation: Owners' Rights, Title Transfer, Security and Legal Risks

Owners, a vested engineer and contractor representatives at a meeting table over project plans and a building model; buildings under construction and a crane in the background. The Güneş & Güneş logo and the article title on the left.
Author: Published: About 52 min read

Institutional legal review and control: Güneş & Güneş Law Firm

Published by: Güneş & Güneş Law Firm

Summary

A flat-for-land (land share in exchange for construction) contract in urban transformation does not merely provide for demolishing the old building and constructing the new one; it regulates together the owners' land shares, their rights to the new independent units, the contractor's financing, title transfers, security, the construction schedule and the consequences of possible disputes. A pure-majority decision based on shares under Law No. 6306 does not mean that all owners have signed the same private-law contract. In particular, early title transfer to the contractor and sales to or mortgages in favor of third parties must be managed far more carefully in light of the Court of Cassation (Yargıtay) Unification of Case Law Decision of 16.05.2025. This guide considers together the regulation amendment of February 4, 2026, the owners' meeting and the offer notification, the technical allocation, security, default, termination, evidence and remedies, and offers a checklist that can be applied before signing. It also examines the contractor's composition (konkordato) or bankruptcy, the bank's mortgage over the property, the actual collection of security, the cost of completing the project and final acceptance as parts of the pre-contract protection plan.

1. Why does a flat-for-land construction contract in urban transformation carry special risk?

1.1. The contract determines more than the construction price

In flat-for-land construction, the contractor performs the agreed construction work and, as consideration, acquires land shares or the rights corresponding to independent units in the new project. The transaction creates a mixed-nature relationship that combines the provisions on the contract for work in Articles 470 et seq. of the Turkish Code of Obligations (TBK) with the form and registration rules on the transfer of immovable ownership. The statement "the contractor will build the building, the owner will receive an apartment" is therefore not enough to describe the parties' true legal position. It must be determined which property will remain with whom, on what date which performance falls due, and to what extent the contractor may use the transferred shares.

For the general structure of the contract, its form and the parties' obligations, see our guide to the land-share (flat-for-land) construction contract and our guide to construction contracts.

1.2. Law No. 6306 and the general condominium rules must be assessed separately

Not every renewal of an old building falls under the special regime of Law No. 6306 merely because the parties use the term "urban transformation". The statuses of risky building, risk area and reserve building area must be verified through the procedure of determination, notification and implementation decisions. The general management/unanimity order under the Condominium Law (Kat Mülkiyeti Kanunu) and the TMK and the special decision and sale mechanism of Law No. 6306 cannot be applied on the assumption that one eliminates the other in every case. The legal status of the parcel must be established first.

1.3. The decision quorum and being a party to the contract are separate matters

Under Article 6 of Law No. 6306 and Article 15 of the Regulation, certain implementation decisions can be taken by at least a pure majority of the shares in the land register, not by the number of owners. According to the special mechanism of the Law, the shares of those who do not join the decision may enter the sales process. By contrast, a pure-majority decision does not by itself create the signature of the non-participating owner, a declaration granting power of attorney, or all the personal obligations in the private-law contract. The addressee of the settlement offer, sale, registration, representation and obligations must be shown separately. In particular, general wording in a contract drawn up in favor of the majority that the minority owner automatically becomes a party gives rise to legal disputes.

2.1. Current title deed, encumbrances, shares and representation

Owners' share ratios, condominium ownership/condominium easement records, mortgages, attachments, usufruct, family home, sales-promise annotations, zoning implementations, and inheritance or partnership relationships must be examined together. If the title deed record and the signature table of the meeting do not carry the same date, the majority may change. For heirs, shareholding companies and owners represented by an attorney, the authority documents and the need for special authority are assessed separately. The majority must not be calculated using only an old list prepared by the building management.

2.2. Risky building determination and the finalization process

The risky building report, notifications to owners and objection records, the technical board's result, the title deed declaration and the evacuation/demolition stage must be in the file in chronological order. Under Article 7 of the Regulation, an objection to the risky building determination is provided for within fifteen days from the last day of the announcement at the muhtar's office, to the competent Directorate/Administration; this period does not automatically carry over to a different administrative act or a judicial remedy. Not objecting does not mean accepting every contract term within the scope of the administrative act. An administrative action in which a stay of execution is not requested or not granted does not stop the implementation by itself.

2.3. Zoning status, building rights and architectural feasibility

The commitment on allocation cannot be determined safely without examining the zoning certificate, plan notes, floor-area ratio, height, setbacks, parking, shelter, fire regulations, soil survey, and the areas of existing and new independent units. The number of independent units offered by the contractor is not a guarantee of the permit the administration will issue. In particular, clauses such as "if the floor-area ratio increases, all of it belongs to the contractor" or "the allocation will be redetermined according to the permit" may leave essential performances uncertain.

That the title deed record of a property looks clean does not mean that a building permit can be obtained or that the existing project can be implemented as promised in the contract. Current ownership and encumbrance records, zoning status, risky building status, floor-area ratio/parking conditions, owners' decisions, condominium easement/condominium ownership data and the old project should be checked against a common chronology. If the share list that formed the basis of the owners' meeting and the contract's allocation schedule do not match, an explanation and a corrected table should be requested before signing.

Ongoing administrative cases affecting building rights, the conditions for lifting existing mortgages, the need for consolidation with other parcels, lease rights or use restrictions, circumstances affecting the registrability of ownership and the possibility of zoning plan amendments should be recorded in detail in the risk record. The document check in this guide does not replace the examination of the owners' actual file documents.

3. How is the owners' pure-majority decision taken; how is the minority owner protected?

3.1. Calling the meeting under the February 4, 2026 amendment

Under Article 15 of the Regulation, at the request of one of the owners, all owners of a risky building parcel are called to a meeting. The place and time of the meeting are announced using the Ek-12 form at the relevant muhtar's office or, if the building has not yet been demolished, on the building door/notice board for fifteen days, or notified through a notary. If the announcement method is chosen, the notification is deemed made on the last day of the announcement. The file must contain how the call was made, the start/end dates of the announcement, the minutes, the attendance list, the powers of attorney and the current share calculation. The call to the meeting, the meeting, and the offer notification made afterwards to those who did not join the decision are three separate acts.

3.2. On what value is the majority calculated?

In a building with ten independent units, if six owners come together and their land shares do not exceed half in total, that may not be sufficient. Conversely, if two owners' shares exceed half, they may meet the decision majority in the relevant special procedure. The table should therefore keep the columns "number of owners / number of independent units / land share in the title deed" separate. Any independent dispute that the title share is wrong and possible correction procedures are also assessed for their effect on the timing of the decision.

3.3. The settlement offer and the fifteen-day acceptance period

The content of the decision taken by pure majority and the terms of the agreement, or the place where they can be reviewed, must be properly notified to those who did not join the decision. A notification made to an electronic notification address declared at the land registry is deemed made at the end of the fifth day following the date it reaches the address; for an announcement at the muhtar's office, the last day of the announcement is what matters. The fifteen-day period granted for acceptance from that date cannot be merged with the fifteen-day announcement period of the meeting call. It must be documented whether a real opportunity to review the terms was given and which text the addressee was asked to accept.

3.4. Sale of the shares of non-participating owners

Under Article 15/A of the Regulation, in the sale the application documents, the Value Determination Commission (Bedel Tespiti Komisyonu) and the Sales Commission, the appraised value, the auction announcements, the circle of buyers and the possibilities of later sales are examined according to the status of the transaction. The participant arrangement in the first auction and in later sales is not the same. The provisions on a risk area, a reserve building area and a risky building parcel are not treated as identical. There are cases in which the decision and share-sale mechanism can be operated before the building is demolished; this does not mean an exemption from all notification and valuation requirements. In disputes over the appraised value, the effect of cancelling the sale on ownership or on the price difference must be addressed separately under the special regulation.

We have discussed the remedies against the sale of the share of an owner who did not join the decision in our article objection to the sale of a land share in urban transformation.

3.5. The key documents and periods in the minority owner's defense

A defect in the call to the meeting, vote calculation with old title shares, an unauthorized power of attorney, a missing or closed offer, irregular notification, a low/incorrect appraised value, the sale being carried out at the wrong stage and the absence of Law No. 6306 status are different objections from one another. The owner must determine which administrative act is being targeted and the date of notification/learning; the statutory period in the relevant judicial remedy and, if necessary, a request for a stay of execution should be assessed separately. A general objection merely that the contractor's contract is unjust does not by itself stop the administrative sale.

3.6. Matrix of periods, jurisdiction and interim protection for administrative acts

The objection to the risky building determination, the owners' majority decision, the sale of the non-participating share, the determination of the sale price and zoning/permit acts are not the same act. For a remedy against each, the authority that issued the act, the form of notification/announcement, the date of learning, the objection or action period under the special legislation if any, the competent judicial branch and the stay request must be determined separately. Although the general administrative action period in Article 7 of the Administrative Procedure Law (İYUK) may be taken as a basis, if the special action period of Law No. 6306 or other special provisions exist, they are researched first; a single period is not applied to all acts.

Act to be examinedDocument and starting point to be checked firstLegal protection question
Risky building determinationMuhtar's office announcement, objection minutes, technical report, finalizationThe right of objection in the Regulation and, separately, the conditions of an administrative action
Meeting call and majority decisionEk-12 call announcement/notary notification, title share table, signed decisionThe effect of a defect in the meeting and majority on later implementation
Settlement offer to the non-participating ownerFull content of the offer, electronic/notary/announcement notification and acceptance periodWhether the fifteen-day acceptance right can actually be exercised
Sale of the share by public auctionValue determination, sale call, auction minutes, registrationLawfulness of the sale and stay of execution
Permit and zoning actApproved project, permit, amendment/posting-notification dateThe appropriate administrative action and interim protection route

Warning on periods: This table is not a fixed schedule of periods; the calculation of periods must be made on the basis of the law in force on the date of the act and the current notification document. Filing an administrative application or action does not by itself stop demolition, the sale of shares or the implementation of the permit in every case. The conditions for a stay of execution and, if necessary, an urgent application should be assessed.

3.7. The valuation and defense file for the non-participating owner

Examination of the appraised value is not just the conclusion page of a report. The dates of comparable sales, the parcel's zoning and commercial character, location, building restrictions, premium value (şerefiye), actual use and reasoned adjustments are compared. The valuation expert's report is not the same as the Value Determination Commission's administrative authority to determine value. The objection to the sale price and the claims about the lawfulness of the sale transaction have their legal bases determined separately. The non-participating owner should show, with dated documents, situations in which access to all annexes of the decision was prevented, the offer made remained unclear or the share calculation was wrong.

4. How are the land share, the allocation of independent units and the premium value (şerefiye) secured?

4.1. The old land share is not the automatic equivalent of the new independent unit's value

The land share in the old title deed is the basic data that affects the decision majority in urban transformation. The area, floor, orientation, façade, intended use, view and access of the independent units to be given to the owners in the new building may differ. The land share proportionate to value under Article 3 of the Condominium Law and the premium value calculation should be explained in the allocation schedule. Wording such as "everyone receives the equivalent of their old apartment" or "the square meters will be finalized in the project" leaves it uncertain who will bear the technical or economic differences.

4.2. How should the allocation annex be drawn up?

The main contract should be tied to a numbered independent unit allocation schedule as of the signing date, a table of the former situation based on the current title deed/share, the project reference, the minimum net usable area, floor–façade/location, technical equipment, annexes/parking/storage, and the method of monetary or in-kind equalization of differences. If the permit is later changed, it should be stated which area is unchangeable, which revisions require the owner's written approval, and the sanction for changes made without approval.

4.3. Proof in a premium-value dispute

The valuation expert's assumptions, the approved architectural project, market comparables, usage advantages and the owners' old rights are matched. Not only a computer drawing or sales brochure prepared by the contractor, but the annexed schedule accepted by the parties and an independent technical report should be the basis. Since the legal basis of a claim for cancellation, registration, price difference or compensation may differ, the choice of claim should be made at the start of the dispute.

4.4. Net and gross area, independent unit identity and the procedure for project changes

The allocation schedule should not contain only "3+1 apartment" or a number. Floor, façade, independent unit number, the measurement rule by which net area is calculated, gross area, balcony/terrace, storage, parking, annexes, land share and delivery quality should be tied together. A number change, or project revisions that alter the apartment's position or usage value, should not be left to the contractor's unilateral disposition without a predefined owner approval and premium-value equalization.

In a project revision, first the approval of the competent administration, then the concrete effect on the owners' rights and the balance of counter-performance should be examined separately. Obtaining a permit does not mean that the owner has given up the independent unit agreed in the contract. For events such as a zoning plan amendment, soil improvement or a parking requirement, the contractor's cost burden and the mechanism for the owners' written approval should be regulated in the contract.

5. How is the contractor's financial and technical capacity investigated?

5.1. Company identity, representation, history and financial capacity

The trade registry, partnership/management changes, signing authorities, the contractor's building-contractor authorization status, completed past projects, ongoing obligations, the financing plan and basic financial indicators are checked before the contract. An advertising catalog alone, the statement "we have completed many projects" or the company's founding date is not proof of financial capacity. Bankruptcy and konkordato records, company connections and the real limits of the guarantor's/surety's liability are examined from lawful and accessible sources.

5.2. Project financing and encumbering the parcel

It must be determined how much cash is needed at which stage of work, the proportions of equity–loan–sales advance in the financing, and unforeseen costs. Although the contractor's need to obtain financing is real, it is not necessary to turn the owners' title deeds into an unlimited pool of security. For credit use and mortgages, the maximum amount, authority, beneficiary, independent unit, lifting condition and the position of third parties must be clearly determined.

5.3. Subcontractor, occupational safety and insurance

The contractor's use of a subcontractor does not by itself remove its contractual liability to the employer/owner. The site organization, obligations under Law No. 6331, third-party financial liability, construction all-risks insurance, project and construction defects, the duration of the security and policy exclusions should be regulated according to the real risk of the work. The existence of insurance does not mean that every loss is covered.

5.4. Contractor risk from konkordato, bankruptcy and enforcement proceedings

Not only the contractor's current cash position but whether its ability to pay can be maintained until the work is completed should be examined. The trade registry, changes in the company's capital and partnership, powers of representation, konkordato announcements and decisions, bankruptcy and liquidation information, accessible public records, the financing needs of ongoing sites and financial data obtainable through independent verification are assessed together. Third-party information that is legally inaccessible cannot be presented as the assumed result "has no debt".

A konkordato moratorium, the opening of bankruptcy, attachments and changes in the ownership of company shares do not produce the same legal consequences. The konkordato provisions in Article 285 et seq. of the Enforcement and Bankruptcy Law (İİK) and the bankruptcy estate and disposition regime are applied to the fate of the contract in the concrete file. The generalization that all contracts will end automatically, all security will be liquidated, or all title deeds will return to the owners merely because a konkordato application was made is not correct. The valid conditions for termination, court decisions, ongoing performances, third parties' rights in rem and the independent legal structure of the letter of guarantee are examined separately.

A contract protecting the owners should contain an early-warning obligation, periodic submission of financial records, financing allocated to the project, a work-stoppage criterion, if necessary independent technical and financial supervision, preservation of the security's duration, and a procedural plan for justified termination and transfer of the project. In case of the contractor's financial difficulty, the first step is not only to send a notice: the title deed, the mortgage, third-party transfers, completed works, the materials in the project and the current state of performance under the contract must be documented together.

For half-finished construction, title deeds and claims records in case of the contractor's bankruptcy or konkordato, see our article what happens if the contractor goes bankrupt.

5.5. Allocation of subcontractor, labor, social security and site safety obligations

The contract cannot be resolved by writing "all liability belongs solely to the contractor" in a way that prevents employer status from being determined under the specific law. Mandatory legislation applies to work accidents, employees' wages, social security (SGK) premiums, building supervision, and environmental and permit obligations. For obligations that may arise in the owner's name, foreseeable recourse and indemnity provisions, insurance coverage, document submission and supervision of transactions made with the subcontractor should be provided for. Replacing the subcontractor is not the same transaction as transferring the entire work or releasing the main contractor from the debt.

6. When should the title be transferred to the contractor; what is the risk of sale to third parties?

6.1. Why does advance title transfer create a critical risk?

Transferring the land share to the contractor before construction is completed means the owner parts with the right in rem before receiving the counter-performance. The contractor may sell this right to a third party or encumber it with a mortgage. In a possible termination or invalidity dispute, the assumption that the title deed will necessarily return is now especially dangerous. A title deed annotation, security against delay, limiting the shares subject to transfer and staged transfer are complementary instruments but, alone, do not eliminate all risks.

6.2. Court of Cassation Unification of Case Law Grand General Assembly 16.05.2025, E.2024/1, K.2025/2

This decision, published in the Official Gazette of 18.07.2025, accepted that a third party who acquires an immovable/land share or a mortgage right from the contractor may have its good-faith defense based on TMK Article 1023 heard, in a dispute over a declaration of invalidity or retroactive termination of the land-share construction contract. If bad faith is not proven in the concrete case, the ownership or mortgage acquired may be protected; where bad faith is established, return to the landowner may come into question. The decision neither says "everyone who buys from the contractor is necessarily protected" nor continues the understanding that "everyone who takes over before the construction is finished acts in bad faith". The subject and limit of the decision must be assessed separately with regard to the initial transfer and the land registry records and actual knowledge at the third party's acquisition.

6.3. Staged transfer, annotation and security combination

In the practical protection model, the transfer of the shares to be earned is tied to documented construction progress stages, an independent technical inspection report, a registration instruction duly issued, and real security in the owner's favor. The transfer of the shares allocated to the contractor is planned so as not to lead to the loss of the whole property at once. The existence of an annotation is not by itself a guarantee that all of the third parties' rights will be extinguished upon termination; the type, rank and validity of the annotation, the moment of the third party's acquisition and the concrete question of good faith must be examined together.

6.4. Limiting the mortgage and financing authority

If a mortgage is to be established over the owners' shares or independent units for the contractor's debt, the parties, the maximum principal and accessories, the scope of security, the conditions of liquidation, the moment of lifting and the limits of the owner's consent must be clear. An authority such as "may perform all transactions necessary for financing" is so broad that its economic consequences cannot be foreseen. Obligations affecting the owners' individual ownership must be reviewed separately under the law of representation and land registry practice.

6.5. The May 16, 2025 Unification of Case Law Decision: the dispute, the holding and the evidentiary result

The decision of the Court of Cassation Unification of Case Law Grand General Assembly dated 16.05.2025, E.2024/1, K.2025/2 was published in the Official Gazette (Resmî Gazete) No. 32959 of 18.07.2025. The decision concerns the fate of rights in rem where, after the landowner transfers a share to the contractor at the land registry, the contractor sells this share/independent unit to third parties or establishes a mortgage in favor of a third party, and the main contract is then invalid or ends retroactively.

The tension in earlier practice: The approach proceeding from the premise that the title transfer to the contractor has the character of an "advance" held that, if the contract ended retroactively, the TMK Article 1023 defense of a third party who acquired rights from the contractor could not be heard. In contrast, the approach foregrounding reliance on the registry and protection of the right of ownership argued that real good faith had to be assessed at the moment the right in rem was acquired.

The unified result: The unification decision accepted that the third party's claim of good-faith acquisition of a right in rem relying on the registry can be heard and that, if its conditions are met, the ownership or mortgage right will be protected. On the other hand, if it is shown with concrete facts and evidence that the third party was not in good faith at the relevant time, cancellation of the title deed or deregistration of the right may be considered. The decision does not rule that every third party will necessarily be protected or that the landowner will take back the title deed in every case.

On proof: Within the framework of TMK Articles 3 and 1023–1024, the facts that the parties knew or should have known, the annotations and rights in rem in the title deed record, the price and date of the transfer, the level of construction progress, the relationship between the third party and the contractor, and whether accessible warnings existed when the sale or mortgage was established are assessed together. Merely saying "there was a land-share construction contract" or "a termination decision was given" does not by itself prove the third party's bad faith. Evidence to the contrary in the concrete case should not be withheld either.

Contract strategy: Tying title transfer to objective, independently supervised construction stages, keeping the amount transferred proportionate to the actual value of the work, having the security take effect before the transfer, and limiting permission for sale/mortgage to third parties may reduce the owner's need for post-litigation protection. The title deed annotation and the prohibitions in the contract cannot, however, be presented as producing an automatic absolute result against all third parties without verifying their concrete characteristics.

Primary source: Official Gazette, 18.07.2025, No. 32959, Court of Cassation Unification of Case Law Grand General Assembly E.2024/1, K.2025/2.

For a third party's good-faith defense, see our article cancellation of a title deed bought from the contractor and good faith.

6.6. Bank project financing: the mortgage over the owner's title deed and the release plan

The contractor's use of a project loan and the owner's agreeing to place a mortgage on its own share are different transactions. First, who the loan debtor is, whose property the mortgage is established over, the maximum limit and scope of the security, the conditions of loan disbursement, the allocation of the money to the project, the bank's enforcement and sale powers and at which concrete payment or construction stage and how the mortgage will be released must be determined. Promises such as "all mortgages will be lifted at occupancy" that have no acceptance by the bank or binding release mechanism do not constitute security.

Creating a direct personal debt or suretyship in the owner's name and merely indicating a particular property as security in rem are not the same liability. The bank's and the contractor's transactions in the loan agreement are not automatically reflected in the owner's contract. If a mortgage is to be established, permission to transfer title should not be given without a staged release accepted by the bank, a blocked account or an appropriate guarantee system that secures the owners' counter-performances. The 2025 unification decision is also of separate importance with regard to the third party's mortgage right.

7. Form of the contract, notarial act, annexes and power of attorney

7.1. Official form and the inseparable annexes of a valid contract

The immovable transfer/promise element in land-share construction contracts must be assessed under the mandatory official form requirements appropriate to its legal nature. It cannot be said that a merely signed private written protocol is sufficient in every case. The notarial drawing-up, the authority of the land registry to conduct the transaction, the owners' power of representation and whether amendment protocols are subject to the same form regime are examined concretely. The main contract should not be signed leaving essential performances uncertain on the ground that technical details will be created later.

7.2. Main contract, technical specification and document priority

The main contract should contain the parties, the title deed and obligations, the share allocation, the fixed term, security, title transfer, defects, delay, termination and liquidation provisions. The room schedule, structural/architectural/mechanical/electrical drawings, the work program, the work and material brand/performance criteria and warranty documents may be detailed in a separate technical protocol. If there are conflicts among the annexes, it should be stated which document and revision prevails. Oral amendments without documents are among the main sources of later proof problems between the contractor and the owner.

7.3. Power of attorney and authority to amend the contract

The signing authority of the owners' representative should not be accepted as unlimited for transactions such as amending the contract, transferring shares, establishing a mortgage, waiver, settlement, acceptance of performance and an evacuation undertaking. The limits per transaction and per property should be kept clear in the power of attorney; if there is a board/representation committee, the decision minutes and the relationship with minority rights should be documented. The administrative decision mechanism of Law No. 6306 does not create the authority to carry out personal acts in the owner's name without a valid power of attorney.

7.4. Assignment of the contract, change of partnership and the limits of the owners' representative

The contractor's merely appointing a subcontractor, assigning its position in the contract to another company and the transfer of company shares are separate facts. Taking into account the provisions on the assignment of the contract in TBK Article 205 and the other consent/form rules required in the concrete relationship, the risk of arrangements that in fact change the debtor or the liability for the principal performance without the owner's consent should be limited. A prior approval given in the contract for assignment or amendment should not be interpreted on the assumption that it unconditionally satisfies all future transaction conditions.

The scope of the power of attorney given to the representative of the owners' board should be specially determined, particularly for title transfer, establishing a mortgage, accepting payment, changing the project, releasing security, settlement, release and arbitration, and termination. A double-signature, decision and information mechanism may be established against the risk that, with the representative's single signature, the owners' principal counter-performance is reduced or the contractor's basic obligation is eliminated. If abuse of authority emerges, merely revoking the power of attorney does not automatically invalidate past land registry transactions; the concrete transaction and the third party's situation are examined separately.

7.5. The owner's death, inheritance and continuity in properties with multiple co-owners

For shares changing hands through an owner's death or inheritance, the TMK succession and land registry transfer provisions and the nature of the existing contract's obligations and personal performances are examined together. During the process, the majority calculation, title transfer or release cannot be made without verifying the identity and representation authority of the new heirs. If the contractor is a natural person, the effect of death on personal performance, and if it is a legal entity, different rules on the dissolution of the company and representation apply. The power of attorney and notification procedures of owners living abroad should also be planned separately.

8. How should the delivery date, permit and delay sanctions be written?

8.1. The trap of an indefinite period tied to the permit date

A clause such as "the construction period is 24 months from obtaining the permit" is not sufficient alone; if the contractor delays the permit application indefinitely, the start of performance remains uncontrolled. The latest date for applying for the permit, completing missing documents, obtaining permissions, evacuation, demolition, site handover, excavation, rough construction, the occupancy permit and the actual delivery should be set by a schedule in which they are linked to one another. Proving the start of the work with objective documents reduces arbitrary extensions of time.

8.2. Fixed term, notice and TBK Articles 117–125

If a specific performance day within the meaning of TBK Article 117/2 has been agreed, default may arise, subject to its conditions, without a separate notice; maturity, the creditor's conduct and the other provisions of the contract are still assessed. In cases of uncertain dates, whether a notice, an appropriate additional period or statutory exceptions are required is determined according to the concrete case. When writing a delay penalty/penalty clause, rent assistance, real rent loss and additional damages together, care must be taken to avoid the prohibition of double recovery for the same loss.

8.3. The evacuation period and rent support

Who bears the rent burden from the owner's vacating the property until receiving a new independent unit that it can actually use and that can be delivered legally and technically must be agreed. Public rent assistance and the contractor's contractual rent compensation are not the same legal debt; the conditions for possible set-off or joint benefit should be examined under the relevant legislation and the contract. The increase in rent payments, their start, their end, a delay in title/occupancy and the failure of actual delivery must be clearly described.

8.4. Risk allocation in soil, infrastructure and official-permit costs

Who bears the cost of soil improvement, reinforced foundations, retaining/shoring, neighboring property safety, infrastructure relocation, the parking burden or additional engineering projects that may arise in the permit application must be determined. Unlimited transfers of burden such as "all new expenses belong to the owners" may make the balance of the owners' existing performance uncertain. A price increase or a request for additional land share should be linked to a predefined event, an independent technical report, an owners' decision and limits on changes.

The allocation schedule in the owners' favor should show not only the design on the day the contract is signed but also the minimum square meters, type of use, quality and premium-value conditions to be preserved in possible permit revisions. An additional period granted to the contractor and a price adjustment are separate legal decisions.

9. Force majeure, adjustment and excessive onerousness

9.1. Impossibility of performance and cost increase must not be confused

TBK Article 136 is assessed as impossibility; TBK Article 138 in the context of excessive onerousness and adjustment, if its conditions are met. Not every increase in foreign exchange, wage or material cost is force majeure by itself. War, disaster, mobilization, import restrictions or administrative bans may produce consequences only to the extent of their real effect on the contract or performance. Foreseeability at the outset, the contractor's fault, alternative supply and efforts to mitigate loss must also be discussed.

9.2. The contractual force majeure regime

The foreseeable categories should be written clearly; a notification of the event, if possible a short notice obligation such as seven days, evidence, independent technical assessment, effect on the critical work program, partial performance, temporary suspension, a total extension limit and a termination/liquidation mechanism for long-term disruption should be established. However, it should not be assumed that absolute rights arising from the law are eliminated in advance by contract or that every exception is exhausted in advance. A loss arising from an earthquake or natural disaster does not by itself prove absence of fault and liability in every concrete case.

9.3. Rent and security during the extension

In the event of force majeure, all of the contractor's contractual responsibilities do not end automatically. The parties' risk allocation should be regulated separately for rent support, insurance, the duration of the security, site safety and the preservation of project documents. Where the time must be extended, failing to extend the duration of the security as well creates a substantial gap in protection for the owner.

10. How should the security system in the owners' favor be established?

10.1. Bank letter of guarantee and reliability

Although an unconditional/first-demand letter of guarantee may be proposed, the security cannot be regarded as sufficient without checking the bank, the beneficiary, the guaranteed debt, the maximum amount, the final date, the demand procedure and the regulatory conditions of the letter. It must be ensured that the security covers the real loss and delay risk in the contract, that it is verified with the bank, that it is released in proportion to the stages and that it does not become void in cases of expiry.

10.2. Mortgage, suretyship, cash blockage and completion security

Each type of security protects against a different legal event. The personal suretyship of the contractor company's partner, a bank letter of guarantee, a mortgage in the owners' favor, a security account, control of independent unit transfer and completion insurance are not the same as one another. The enforceability, priority, debtor's assets, duration and enforcement procedure of the security must be examined concretely. Instead of nominal or already exhausted security, a combination resilient to the scenario in which the contractor fails to complete should be chosen.

10.3. The real stress test of the security

If the contractor abandons the work in month 30, if rights pass to third parties at the land registry, if the financing bank wants to liquidate the mortgage, or if costs rise, which security can actually be used? The amount of the security, the documentary demand condition, the expiry date, which owner will use it and dispute resolution should be audited through these questions. What should be treated as decisive is not the existence of the security but the possibility of collection or completion at the moment of breach.

10.4. Collection, bankruptcy and expiry scenarios by type of security

An independent guarantee given by a bank, the personal suretyship of the contractor company's partner, a mortgage over property, cash blockage and insurance do not provide the same legal protection. For this reason, not only the total nominal amount but at which moment of breach, which document will be presented to which authority and from which assets collection will be made should be examined. In particular, in a company's konkordato or bankruptcy, the validity of the security, the guarantor's independent debt, the term of the letter of guarantee, the guarantee conditions, the owner's capacity as beneficiary and the notification/application conditions are decisive.

Protection instrumentWhat must be checkedExample of where it falls short
Bank letter of guaranteeBeneficiary, condition, amount, term, extension, demand text, bank verificationThe letter having expired when the work stops
Personal suretyshipValid form and consent conditions, the person's assets, suretyship limitThe surety also being unable to pay its debts
MortgageRank, scope of security, earlier mortgages and order in the saleThe value of the pledge not being sufficient to cover the other creditors
Cash blockage/escrow accountDouble control and set-off on withdrawal from the accountThe money being withdrawn by the contractor before the security is used
Insurance/policyInsured risk, beneficiary, deductible, exclusion, notification of lossThe risk of non-completion not being in the policy at all
Staged title transferDetermination of work progress, progress payment, definition of the independent unitThe title passing to a third party before the work is actually done

The principle that becomes a contract provision: The release of the security should be tied not to a unilateral contractor report but to independent technical confirmation, the performance of the owners' rights, any defect/outstanding-work reserve and real documents that the possibility of a justified claim does not continue. Statements that the bank security or insurance covers all risks should not be used without examining the original policy and letter text.

10.5. Distinguishing site insurance from completion security

Construction All Risks, third-party liability, employer's liability and other policies, according to their scope, may cover physical damage or liability risks; the contractor's abandoning the work due to financial inadequacy is not by itself the subject of cover under each of them. Instead of merely writing the name in the policy summary, the special/general conditions, exclusions, deductibles, sum insured, insured and beneficiary, and duration should be examined. If it really exists for the project's completion security, a separate solution specific to it should also be established under security law.

11. Supervision, work program, defects, occupancy and delivery

11.1. Independent technical control

The owners' technical control representative should be able to follow the percentage of work, conformity to the specification, occupational safety and progress documents. The contractor's own report should not replace independent supervision by itself. The stage on which title transfer or the security solution is based should be tied to an expert report and photos/minutes; records should be kept for hidden works, reinforced-concrete elements, installations and waterproofing, which are hard to see later.

11.2. Actual delivery, acceptance and the building occupancy permit

Handing over the key, provisional acceptance, actual use and the building occupancy permit document are different facts. The contract should describe which stage is "delivery" and without which document delivery cannot be deemed complete. Outstanding works, defects, obstacles to use, common areas, elevator, fire and mechanical systems, and the transition to condominium ownership should be checked separately.

11.3. Notice of defects, limitation period and warranty

Under TBK Articles 474–478, the inspection of the work, open/hidden defects, notification and the rights arising from defects are assessed together with any additional warranty in the contract. Clauses by which statutory liability is eliminated entirely in a way that is not legally possible should be examined separately. Reservations written in the delivery minutes, the outstanding-works list, photos, test reports and notices carry evidentiary value.

11.4. Transition to condominium ownership, common areas and release of security

The process should not be deemed over with the actual delivery of the apartment. The transition from condominium easement to condominium ownership, the building occupancy permit document, correction of type, independent unit definitions consistent with the architectural project, the management plan, common areas, parking, elevator, fire, shelter, energy performance and infrastructure acceptance documents should be regulated as a delivery set bound by the contract. The final transfer of the contractor's shares and the release of the security should be tied to all these documents or to stages justifiably determined.

Writing in the delivery minutes that "all works were received without defects" does not make hidden defects or common works not yet done invisible; the real scope of the parties' statements is still examined. At the acceptance stage there should be a clear outstanding-works list, a remedy schedule, a price security reserve, technical tests and a person responsible for the final check. If an additional warranty beyond the statutory defect rights is to be given, which work and which period it covers and its fate if the contractor changes should be determined.

12. Termination of the contract if the contractor abandons the work and continuation with a new contractor

12.1. Default, TBK Articles 473 and 123–125

If the contractor never starts the work or it is clearly seen that the construction cannot be completed within the agreed period, remedies may come into play within the statutory conditions without waiting for the delivery date. However, which notification, additional period, notice or court decision is required varies according to the nature of the contract, the level of work achieved and the claims. In land-share construction in particular, merely writing the word "termination" does not resolve the liquidation of the title deed and the work done.

12.2. Termination/withdrawal, liquidation and third parties' rights

Retroactive withdrawal, termination with prospective effect, invalidity of the contract and justified/unjustified termination are distinguished from one another. The completion ratio of the construction, the counter-performance received by the landowner, the contractor's expenditures, unusable independent units, third-party title deeds, mortgages, security and loss calculations should be assessed as a whole. Because of the 2025 Unification of Case Law Decision, a contract or publication statement to the effect that "when termination occurs, all title deeds return automatically" is not reliable.

For the return of title deeds and liquidation after termination, see our article termination of the land-share construction contract and return of title deeds.

12.3. Transfer to a new contractor and project continuity

Signing a new contract without obtaining from the old contractor the project, permit, structural calculations, warranty files, site minutes, work program, progress payments, and warranty and insurance records complicates the calculation of outstanding work and liability. The new contractor's liability for defects in earlier work, the completion conditions, cost sharing and the fate of the old security need to be regulated in writing. A settlement or liquidation protocol between the parties may not automatically eliminate third parties' rights in rem.

After learning that the work has actually stopped or that the contractor has entered a konkordato/bankruptcy process, the first task of the board/representatives should be to record simultaneously the title deed and encumbrance records and the current site situation. The forty-eight hours here are not a statutory period but an example internal-organization target aimed at reducing loss of evidence. It cannot be concluded that all legal rights can be exercised the same day or that every notice will be counted as timely.

Technical work measurement and photos, the active permit/project, the ownership of equipment and materials on site, third-party sales, the term of ongoing mortgages and bank security, rent collected and public support, subcontractor claim assertions and the extent to which the owners have performed their own obligations are documented. After the contractor's assets and the relevant court decisions have been seen, the decision is made on calling the security, a protective measure, and continuing or ending the contract.

12.5. Calculating the liquidation and completion cost after termination/withdrawal

In the liquidation calculation, the work completion ratio alone is not sufficient. The technical value of work completed in accordance with the contract, the cost of remedying missing and defective work, ensuring site safety, the new contractor's price, project change and permit renewal expenses, the rent or other items paid by the owners, the fate of shares transferred in advance to the contractor and third parties' rights in rem are calculated together. TBK Articles 125 and 473 and the special contract provisions determine which claim is possible; claims for positive/negative damages and for performance/restitution must not result in double recovery.

An agreement made on the transition to the new contractor does not mean that claims against the previous contractor are released merely by the intent to renew. At the same time, in cost equalization and project use, which earlier works the new contractor takes over, which it accepts as defective and which insurance and warranties continue should be determined in a signed technical handover protocol.

13. Which lawsuits and protection routes are considered in a dispute?

13.1. Administrative process and private-law claims are separated

A remedy against acts such as risky building determination, share sale, public-authority notification, permit and demolition, and claims for the contractor's defective performance, rent compensation, title transfer, termination and contractual security are not the same case. Jurisdiction and venue, mandatory mediation as a condition of action, and the appeal route are determined claim by claim and party by party. The place where the immovable subject to the action is located, the company's head office, the venue clause in the contract and the administrative venue regime may not be the same.

A lis pendens annotation on the title deed, a precautionary injunction, a precautionary attachment, a stay of execution and the preservation of evidence depend on different conditions. The conditions of one are not automatically applied to another. In the face of the danger of transfer to third parties, the risk of establishing a mortgage, and irreversible consequences in the demolition or sale process, appropriate legal protection should be assessed in time. For acts to which an application has no automatic suspensive effect, whether an express protective decision from the court is needed should be examined separately.

13.3. Proof and evidence management

The notarized contract, all its annexes, current title deed records, meeting calls, attendance lists, offer notifications, the SPK valuation, independent technical reports, bank guarantees, progress payments, project revisions, photos and records of actual works, the date the construction stopped, rent payments, notices and third-party transactions should be filed in a chain of dates. Legal characterization is not sufficient without evidence, nor is a technical report not tied to the outcome of the claim.

13.4. Mediation as a condition of action, arbitration, jurisdiction and venue agreements

That a dispute arises from a land-share construction relationship does not mean that there is a single competent court or mandatory mediation rule for all claims. The parties' status as merchants, the commercial nature of the dispute, the possibility of consumer law, claims relating to a right in rem in immovable property, administrative acts and mixed/ancillary claims are characterized separately. An arbitration clause in the contract may not automatically apply to all owners, third parties or administrative-court acts. The venue clause should be compared with the exclusive venue provisions of the Civil Procedure Code (HMK).

13.5. Evidence and decision matrix to prevent loss of rights

EventPrincipal evidenceFirst legal assessment
Permit period exceededApplication records, letter on missing documents, delivery minutesFixed term, notice and default
Progress report being contrary to the factsIndependent technical determination, photos, building supervision recordThe condition for stopping title transfer/security release
Title sold to a third partyCurrent title deed with transfers, annotation, notary recordsRights in light of TMK Arts. 1023–1024 and the 2025 Unification Decision
Project stoppingWork determination, work program, correspondenceTBK Arts. 473, 123–125, interim protection and liquidation
Konkordato or bankruptcyCourt announcements/decisions, security documentsClaim, enforcement and guarantee possibilities under the concrete regime
Rent assistance cut offPayment records, delivery conditionsSeparating public support from the private contractual debt
Share saleMeeting, announcement, notification, commission, auction recordsPeriod, administrative act and stay of execution

The basic principle: Merely saying "a lawsuit should be filed", without making the protection request concrete, is not sufficient. Which right is under threat, which act is requested to be stopped, which competent court will be applied to and by which document proof will be made must be determined separately.

14. Concrete risk matrix of contract clauses

Contract headingRisky practiceWhat to check in the owners' favor
Share allocation"To be redetermined after the permit"Signed allocation schedule, net area, premium value and change approval
Term"24 months after the permit"A last date for the permit, an objective start and a fixed delivery
Title transferTransfer of all shares before constructionStages tied to construction, verified progress, limits on transfer
FinancingUnlimited mortgage authority for the contractorMaximum amount, subject and obligation to lift
Security"The contractor will provide security"Bank/debtor, amount, term, demand conditions, independent verification
Force majeure"Every event including economic developments"Narrow definition, real effect, notice, upper limit, continuation of rent/security
DeliveryKey handover onlySeparating tests, common areas, outstanding items and the occupancy permit
Termination"On termination, title deeds are returned"Liquidation, third party's TMK 1023 position, security and a new-contractor plan
Minority ownerTreating the majority decision as an automatic contract signatureSeparating notification, offer, sale and private-law intent
DisputeGeneral and vague "all powers"Administrative/private-law routes, injunction and the right claim outcome

14.1. Example risky wording in drafting the contract and safe audit principles

The comparisons below are not provisions ready for signing; they are example audit criteria explaining the risk carried by certain contract entries. The final contract provision should be written after seeing the project, the land share schedule, the bank arrangement and the title deed status.

Risky or inadequate wordingProvision to be made concrete in the owners' favor
"Delivery within 24 months from obtaining the permit."The last day for the permit application and for the permit, objective site handover, work program and a fixed completion date
"The contractor may establish the mortgage it deems appropriate with a bank."The share to be mortgaged, upper limit, bank acceptance, project account, staged release and owner's approval
"The contractor makes the necessary project changes."Minimum independent unit rights, priority of annexes, premium value and written approval for essential changes
"With force majeure, all periods are automatically extended."Proof of the event by documents, the affected work item, notification, maximum extension and preservation of the security's duration
"The security is returned at rough construction."Independent technical report, completion/defect reserve, staged release according to the occupancy and delivery stages
"The company may assign the work if it wishes."Legal form of the assignment, owner's approval, the new contractor's security and the fate of earlier debts
"On termination, all title deeds are taken back."Third parties' rights in rem relying on the registry, mortgage, the 2025 Unification Decision and the applicable liquidation method

14.2. The risk matrix should consist not only of the clause but of the sanction and the evidence

When auditing a contract provision, six separate questions should be asked: what is the performance the contractor will carry out; what is the measurable final date; by which document is performance proven; in case of breach, which legal right does the owner resort to; is a notice or court decision required for the claim to materialize; and, if the contractor falls into payment difficulty, by which security is the right met? The sentence "contractual penalty and compensation rights are reserved", which answers none of these questions, does not by itself constitute effective protection.

15. The owners' 30-item checklist before the contract is signed

  1. Have the parcel's status under Law No. 6306 and the transaction chronology been documented?
  2. Have the risky building report, objection and finalization records been examined?
  3. Have the current title deed and each owner's land share been verified?
  4. Have mortgages, attachments, annotations, easements and other encumbrances been checked?
  5. Was the meeting call made properly to all owners?
  6. Were the call announcement and the final offer notification kept separate?
  7. Was the decision calculated according to the pure majority of the shares?
  8. Has the authority of attorneys and company representatives been verified?
  9. Have the notification and acceptance periods of owners who did not join the decision been recorded?
  10. Have the valuation, share sale and public auction conditions been examined separately?
  11. Have the zoning status, floor-area ratio, parking, shelter and building limits been verified?
  12. Has the contractor company and its representation authority been checked from the registry?
  13. Have earlier completed works and financial capacity been assessed with documents?
  14. Has the risk to the owners' shares been identified in the financing plan?
  15. Has each independent unit been described one by one in the allocation schedule?
  16. Have net area, floor, façade, storage, parking and annexes been determined?
  17. Have the premium value and the equalization method been agreed?
  18. Have the versions of the architectural/structural/mechanical/electrical annexes been locked?
  19. Are the technical specification and material performance concrete?
  20. Have last dates for applying for and obtaining the permit been set?
  21. Is there a schedule for evacuation, demolition, site handover, construction and fixed delivery?
  22. Have rent assistance, delay penalty and loss calculation been written without overlap?
  23. Is title transfer to the contractor tied to independent technical progress supervision?
  24. Are there concrete limits against the risks of sale and mortgage to third parties?
  25. Has the risk of reliance on the land registry been assessed in light of the 2025 Unification Decision?
  26. Has the collectability of the bank guarantee, suretyship or other security been tested?
  27. Are the force majeure, notice, extension of time and rent/security provisions clear?
  28. Have technical supervision, defects, acceptance and the occupancy permit been regulated?
  29. Have default, termination, liquidation and the new-contractor scenario been written?
  30. Have the administrative and private-law remedies and the preservation of documents been planned?

15.1. Additional complementary audit to the thirty-item checklist

The following additional set of checks should be used so that financial difficulty and project termination risks in particular are not overlooked:

  1. Have accessible konkordato, bankruptcy, liquidation and company authority records been checked for the contractor?
  2. Is it documented which bank and which security will provide the project financing?
  3. Has the bank accepted in writing the upper limit and the release conditions of the mortgage to be placed on the owner's property?
  4. Has it been ensured that staged title transfer, the independent technical report and the security are tied to the same stage?
  5. Have the beneficiary, term, demand procedure and source of the bank letter of guarantee been verified?
  6. Has a notification and evidence-preservation regime been established for the case that the contractor applies for bankruptcy or konkordato?
  7. In a company change or contract assignment, is there an owner approval and a new-security condition?
  8. Has the distinction been made between statutory liability and recourse on subcontractor, labor and social security risks?
  9. Has the sharing of additional costs for soil improvement, parking and infrastructure been determined?
  10. Is a separately signed allocation schedule ready for net/gross area, floor, façade, annexes and parking?
  11. Is it clear that essential owner rights will be protected in a project revision?
  12. Have occupancy, condominium ownership, common areas and technical acceptance been tied to the scope of delivery?
  13. Is it provided that the security cannot be fully released without preserving the defect and outstanding-work reserve?
  14. Has a person responsible for periods been designated for administrative act notifications, minutes and the need for protective measures?
  15. If the contractor abandons the work, is there an applicable procedure for technical determination, liquidation, a new contractor and third parties' rights?

15.2. Risks that differ by type of owner

For a residential owner, housing and temporary rent costs; for a business-premises owner, architecture/permit appropriate to the intended use and interruption of the business; for an owner of multiple independent units, the land share ratio and a separate allocation for all of the apartments; for an heir or co-owner, joint/shared ownership and representation; for an owner living abroad, notification, apostille and power of attorney; and for an owner who did not join the majority decision, the meeting/offer and share sale procedure come to the fore. These risks should be assessed according to the real personal and in rem rights situation rather than applying the same template contract to all parties.

16. Points to note in urban transformation contracts in Antalya and across Türkiye

In Antalya, Kemer, Muratpaşa, Konyaaltı, Alanya and other districts, tourism, condominium easement, mixed commercial use and different premium values may affect allocation disputes. In other provinces of Türkiye, municipal practices and soil and zoning characteristics vary; national law and private-law principles do not turn into a different regime merely because the province changes. Zoning plan and land registry directorate transactions are examined according to the real administrative geography of the property concerned. The scope of special-transaction authority and translation needs in powers of attorney of owners living abroad, issued by consulate or another appropriate route, should also be audited. This section is for information and does not replace the examination of authority and applicable law in a concrete file.

16.1. Taxes, fees and official transaction costs, and public support

To which property, transaction and party the fee, tax and charge exemptions under Law No. 6306 will apply must be determined together with land registry/permit costs, VAT and other financial obligations according to the regulations currently in force. It cannot be assumed that an exemption for one type of transaction eliminates all commercial contract costs. Public rent assistance and construction/relocation support are different from the rent, completion and defect-remedy debts the contractor undertakes by contract. Who will apply, to whom the support will be paid, the eligibility conditions, possible set-off and the repayment burden must be clearly regulated.

16.2. Post-decision implementation and the 90-day project monitoring regime

The owners' committee needs recorded monitoring not only when the contract is signed but throughout implementation. At predetermined meeting intervals, the permit, foundation/load-bearing system works, building supervision minutes, the duration of the security, title deed changes, delivery risks and rent payments can be compared in a single file. The ninety-day period here is not a statutory requirement but an example administrative monitoring model that can be adapted to the project scale. In case of breach or notification, a shorter period and urgent assessment may be needed.

Even when all stages are completed, the work should not be deemed closed until technical acceptance, the transition to condominium ownership, remedying outstanding works, partial release of the security and final account transactions are finished. The effect of the contract is audited not on the signing day but at the point where the agreed rights are fully realized in the title deed, in the building and in actual use.

Conclusion

In a flat-for-land construction contract for urban transformation, protection does not consist of adding a "penalty clause" after the contract is signed. The correct legal status, a valid majority and notification, a measurable independent unit allocation, performance on a schedule, controlled title transfer, collectible security and realistic termination/liquidation provisions must be built together. The regulation regime of February 4, 2026 decisively affects the procedure for owners who did not join the decision, and the Unification of Case Law Decision of May 16, 2025 decisively affects third parties' rights in rem. Therefore, carrying out a legal and technical review before the title and project are transferred aims, when a dispute arises, not merely to win a lawsuit but for the project to actually be completed and ownership delivered securely.

Frequently Asked Questions

Is it mandatory in urban transformation for all owners to sign the contract?

Under Law No. 6306, special implementation decisions can be taken, under certain conditions, by pure majority according to land share. However, the administrative majority decision does not by itself make the person who did not sign a party to all the provisions of the private-law contract; the statutory sale and representation mechanism applies separately.

In a building with ten independent units, do six owners count as a majority?

The number alone is not sufficient. It is examined whether the total of the signatories' current title deed land shares exceeds half.

Is the 15 days in the meeting announcement the same as the 15 days in the contract offer?

No. The announcement and notification regime of the meeting call, the offer notification made to the owner who did not join the decision and the acceptance period of the offer are tied to separate acts and dates.

Can the share of an owner who did not join the decision be sold before the building is demolished?

When the statutory status and special conditions are met, completion of demolition is not a precondition for all implementation decisions or for the sale of shares. However, the notification, valuation, decision and sale procedure must still be followed.

Is it mandatory to transfer the entire title to the contractor at the start of the contract?

No. Staged transfer, contractor financing and owner security can be planned together. Advance transfer may increase the risk of sale to third parties and of mortgages.

Is the title deed of someone who buys from the contractor cancelled when the contract is terminated?

Not automatically. Unification of Case Law Decision E.2024/1, K.2025/2 of 16.05.2025 provides that the good-faith defense be assessed with concrete evidence within the scope of TMK Article 1023.

Should the land share and the new apartment's square meters be the same?

The land share is the legal value that affects the decision majority. The new independent unit's value, area, floor and façade equivalent should be determined separately by the allocation and premium-value schedule.

Is a 24-months-from-the-permit-date delivery clause sufficient?

Alone it may not be safe. If a maximum period for the permit application/obtaining and a fixed delivery schedule are not set, the start may remain uncertain.

Does the contractor's rent payment obligation end automatically because of force majeure?

No. The effect of the event on performance, the law, fault and the special risk allocation in the contract are examined together; payment and security obligations should be regulated separately.

Is public rent assistance the same as the contractor's rent compensation?

No. The administrative support conditions of one and the contractual debt and loss relationship of the other are different; set-off and joint-benefit conditions are assessed in the concrete file.

What first step should be taken when construction stops?

First, the current state of the contract, the schedule, the level of work, title deed/third-party transactions and the security should be documented; the need for technical evidence preservation and for a notice/injunction should be assessed without delay.

Does the sale stop automatically when an owner who did not join the decision files a lawsuit?

Not in every case. The competent court and judicial route should be determined according to the type of act; if necessary, a stay of execution or other interim legal protection should be requested separately.

If the contractor declares konkordato, does the construction contract end automatically?

No; a konkordato application or a moratorium decision does not end every contract automatically. The moratorium and the ongoing-contract regime under the İİK, the performances of the concrete contract, court decisions and the security documents are assessed together. The owner should examine the title deed, security, work and the action/application period without assuming that the contract has been terminated automatically.

Can a mortgage be placed on the owner's property for the bank's project loan?

A mortgage can be established over a property only with applicable authority, form and title deed conditions. Giving a general mortgage permission without an upper limit in the owner's favor, a loan link, staged release and the bank's written obligations creates a serious risk to rights in rem.

Did the 2025 Court of Cassation unification of case law decision completely remove the right to take back the title?

No. The decision provides for examination of the third party's claim of good-faith acquisition of a right in rem. If the third party's bad faith is established with concrete evidence, cancellation of the title deed or deregistration of the mortgage may come into question; the result depends on the records and evidence of each case.

Does being given the key before the occupancy permit mean the construction has been delivered?

Not in every case. The parties' definition of delivery, fitness for actual use, the building occupancy permit document and outstanding/defective works are assessed separately. Receiving the key should not be interpreted as waiving all statutory rights regarding defects.

If the share of a non-participating owner is to be sold, which documents should be examined immediately?

The current title deed share table, the meeting call and minutes, the full text of the offer and the date of notification, the appraised value report, the Value Determination Commission act, the sale notification and any legal protection decisions should be assessed together. Application and judicial periods are calculated according to the concrete date of notification and the special regulation.

Sources

Date legislation and sources were checked: November 21, 2026.

  1. Law No. 6306 on the Transformation of Areas Under Disaster Risk, in particular Art. 6.
  2. Implementing Regulation of Law No. 6306, in particular Arts. 7, 8, 15, 15/A and 16.
  3. Regulation Amending the Implementing Regulation of Law No. 6306, Official Gazette, 04.02.2026, No. 33158.
  4. Turkish Code of Obligations No. 6098, Arts. 117–125, 136, 138, 470 et seq.
  5. Turkish Civil Code No. 4721, Arts. 2, 3, 1023–1024.
  6. Condominium Law No. 634, Art. 3.
  7. Code of Civil Procedure No. 6100.
  8. Court of Cassation Unification of Case Law Grand General Assembly, 16.05.2025, E.2024/1, K.2025/2 (Official Gazette, 18.07.2025, No. 32959).
  9. Union of Turkish Bar Associations, Announcement 2025/53: On the Decision of the Court of Cassation Unification of Case Law Grand General Assembly.

AUTHOR

Av. Umut Güneş

Güneş & Güneş Law Firm

Send feedback or a correction

You can send us comments or corrections about sources, dates, content or links.

Mentioning the article title and the relevant section is enough. Please do not send personal case details or documents.

GÜNEŞ & GÜNEŞ LAW FIRM

Contact and Consultation

Our Antalya-based law firm, in practice since 1999, offers communication in Turkish, English, German and Russian on legal matters connected to Türkiye.

Whether you are in Türkiye or abroad, you can reach us by phone, WhatsApp, e-mail, in person or by video conference.

Consultation process and information needed